Project Plan – Lesson 7
The
Manage Phase
Planning
Project leadership
Progress monitoring
Process management
Conflict management
|
The students will be told about
the idea for the project 2 weeks before it starts. New ICT tools to be used
during the project (i.e. using a spreadsheet for survey results) will be
practiced before the project launch.
|
Use of the library and computer
equipment will be scheduled and booked in advance.
|
Whole class conference once per week
|
Group Progress
Team checkpoint meetings as well informally
daily checking with teams and individuals on their work.
|
Individual Progress
(7.5) Re-planning:
Since student autonomy is low
there is low risk of the project going off track. 10% additional time
allowance has been included for overrun but the end date cannot be exceeded.
There is an option for homework to be used to catch up if necessary.
|
(7.6) Conflict Management:
Teamwork rules will be included in project launch presentation.
Students are asked to initially try to work out conflicts on their own. In
the case of a deadlock, issues are to be raised with the teacher. Lack of
participation will be dealt with by culprits being removed from the project
work and set to work on alternative individual tasks for the duration of the
project.
|