Waste Management to Increase Productivity - Lesson 7

Project Plan – Lesson 7

The Manage Phase

 (7.1) Process Management:
               
Planning,leadership,monitoring & management of processes & constraints

(7.2) Student Preparation:
               
Students will be told about the idea of the project 2-3 weeks before it starts.A practice will be given on the usage of ICT.

(7.3)  Facilitation:
               
Usage of resources will be scheduled and booked in advance.

(7.4) Progress Monitoring:
               
Whole class meeting once per week.

Group Progress

Meetings with team members and informal daily checking with individuals on their work

         Individual Progress



(7.5) Re-planning:
              
An additional time allowance has been included in case project goes off track but strictly instructed to stick on to the end date. Home assignments can be carried to catch up if necessary.

(7.6) Conflict Management:
               
Team work rules will be included in the project launch presentation. Students are asked to initially try to work out conflicts on their own. In case not possible issues to be brought to the notice of teacher. Lack of participation will be viewed seriously and alternative tasks will be assigned.



Waste Management to Increase Productivity - Lesson 6

Project Plan - Lesson 6The Review Phase


(6.1)Student Reflection and Evaluation:
                
Students will be given an opportunity to reflect their views on: what I learned about and what to learn yet?, what I liked about and what I did not?, what skills I accumulated and how can I improve?.A subsequent lesson will be taken covering reflections obtained from each group of students.

(6.2) Teacher Reflection and Evaluation:
             
Teacher reflection and evaluation will cover the successes, challenges, achievements of the project.

(6.3) Assessment of 21st Century skills:
               
Artifact
21st century skills
Research notes
Logical reasoning,ict,initiative
Survey designs
Creativity, communication
Message board
Teamwork
Presentation outlines
Creativity communication ,ict,initiative

(6.4) Summative Assessment and Grading:
               
Product
Rubric
Grading
Survey results
Survey question and designs

Data sheet
Data sheet

presentation
Project presentation








Waste Management to Increase Productivity - Lesson 5

Project Plan – Lesson 5The Do Phase


(5.1) Project Launch:
              
The project will be launched after a group meeting with the whole class.Every aspect of the project will be discussed .Students will be invited to have an open discussion on the various facts influencing the project. The final presentation will be displayed after printing int the class room as well as in the blog.

(5.2) Artifacts:
              
Students will prepare notes, will design and conduct survey, presentation outlines.

(5.3) Culminating product:
              
Reused plastic bottles based on the creativity will be displayed by the students. Each team will present their views on the project work. Posting in the blog will be presented by the team to the teacher.

(5.4) Celebrating completion:
              
The project will be displayed in the school for other section children to view. A report will be given in the news paper regarding the project to pass a message to the society.

 

Waste Management to Increase Productivity - Lesson 4

Work plan-Lesson 4
Sl.
No
TASK
SUBTASK
ROLE
START DATE
END DATE
PRODUCT

1

Launching project
---------------------
Teacher
07/11/2016
07/12/2016
Project is launched

2
Delivering classroom instruction raising a question
Description of areas to be covered,the scope of project
teacher
08/11/2016
09/11/2016
Initial introduction and instructions  are given
3
Group selection &duty allotment
Student’s list is prepared taking individual differences into consideration
teacher
10/11/16
10/11/16
Group selection & work allotment is completed
4
Primary & secondary data collection
Informations required for the project by each group
students
11/11/16
15/11/16
Information gathered is recorded
5
Survey
Creating questionnaire, surveying and preparing reports.
students
16/11/16
18/11/16
Survey is done
6
Requirements for the work
Collection of materials
students
19/11/16
22/11/16
Materials are collected
7
Starting activities
Designing of the materials
students
23/11/16
26/11/16
Materials are designed
8


Display of designed materials
Designed materials are displayed with plants
students
27/11/16
29/11/16
Planting was done
9
Advice meetings
Team prepares brief
students
30/11/16
30/11/16
Briefing was done
10
Finalising the work
Final analysis of work done
Students & teacher
1/12//16
1/12/16
Analysis was done
11
Compilation of the results
Results obtained was briefed by team members
students
2/12/16
2/12/16
Compilation was done
12
Interpretation of results
Interpretation of project by team members
students
3/12/16
3/12/16
Results was interpreted & conclusions were derived
13
Assessment & grading
Rubrics for assessment to be prepared
teacher
4/12/16
4/12/16
prepared
13
Reflection & evaluation
Reflection & evaluation of work ,expressing views on the project
Teacher & students
5/12/16
5/12/16
completed
14
Presentation of project
Posting in the computer
Teacher
6/12/16
6/12/16

13
Closing of project
Submitting to the PRINCIPAL
Teacher
7/12/16
7/12/16