E - Wastage - Lesson 7
Project Plan – Lesson 7
The
Manage Phase
·
Planning
·
Project
leadership
·
Progress
monitoring
·
Process
management
·
Conflict
management
|
(7.2) Student Preparation:
The students will be told about the idea for the project 2 weeks
before it starts. Usage of Microsoft Excel and Word programs should be
practiced before the project.
Preparation of good questionnaire, qualities of a questionnaire ect.
should be taught to the students.
|
(7.3) Facilitation:
Use of the library and computer equipment will be scheduled and booked
in advance.
|
(7.4) Progress Monitoring:
Daily
before starting normal teaching, 5 minutes discuss with the group leaders on
the progress of their respective task.
Ask
them to record in the log book for the further reference and evaluation.
|
Group Progress
Team
checkpoint meetings as well informally daily checking with teams and
individuals on their work.
|
Individual Progress
(7.5)
Re-planning:
Because of normal study schedule and exams children are not regular in the project. So
the project loose its regularity. 10
days of additional time allowance has been included.
|
(7.6) Conflict
Management:
Teamwork rules will
be included in project launch presentation. Students are asked to initially
try to work out conflicts on their own. In the case of a deadlock, issues are
to be raised with the teacher. Lack of participation will be dealt with by
culprits being removed from the project work and set to work on alternative
individual tasks for the duration of the project.
|
E - Wastage - Lesson 6
Project Plan - Lesson 6
The Review Phase
(6.1)Student
Reflection and Evaluation:
After the presentation of each group ,
students from other group will do the peer group analysis (four students will
say on two strength, two weakness, two opportunities, and two limitation
of the topic/presentation each.
|
(6.2) Teacher
Reflection and Evaluation:
I have prepared a teacher reflection and
evaluation form to complete that covers:
|
(6.3) Assessment
of 21st Century skills:
List of 21st century
skills in this project and its assessment
|
(6.4) Summative
Assessment and Grading:
List products and the
corresponding rubrics that will be used for SA and Grading
Product
|
Rubric
|
Grading
|
Seminar presentation
|
Presentation rubrics
|
|
Power point
presentation
|
Power point
presentation rubrics
|
|
Survey analysis
|
Rubrics for Tabular and graphical
presentation
|
|
Blog portfolio
|
Blog rubric
|
E - Wastage - Lesson 5
Lesson 5
The Do
Phase
(5.1) Project Launch:
The project will be launched as meeting with the
whole class.
There will be a presentation covering goals,
expectations, rules, procedures, assessment and grading.
Students will be invited to discuss any of the above
and we may make change as a result.
The final presentation will be printed and displayed
in the classroom as well as being posted in PBL Blog
|
(5.2) Artifacts:
|
(5.3) Culminating product:
|
(5.4) Celebrating completion:
|
Thursday, 24 November 2016
E - Wastage - Lesson 4
Work plan-Lesson 4
|
No
|
TASK
|
SUB
TASK
|
ROLE
|
START
DATE
|
END
DATE
|
PRODUCT
|
01
|
Launch
project
|
10.11.16
|
10.11.16
|
Project
launched
|
||
02
|
Deliver
classroom instruction
|
Areas
to be covered.
1.Define
the project
2.Culminating
products
|
Teacher
|
11.11.16
|
11.11.16
|
Initial
classroom instruction is completed
|
03
|
Group
selection
|
Students’
list
|
Teacher
|
15.11.16
|
15.11.16
|
Group
selection is completed
|
04
|
Finding
of basic fact by Group I
|
Report/short
note on the basic fact
|
Group
I
|
16.11.16
|
21/11/16
|
Collected
Report
|
05
|
Analysing
the harmful effect
|
Analysis
Report
|
Group
II
|
16/11/16
|
21/11/16
|
Report
prepared
|
06
|
Making
Video clippings on e-wastage management
|
Making
Video clippings
|
Group
III
|
16/11/16
|
21/11/16
|
Video
clippings were prepared
|
07
|
Preparation
of Questionnaire for the survey
|
Questionnaire
with 20 questions
|
Group
IV
|
16/11/16
|
17/11/16
|
Questionnaire
prepared
|
08
|
Conduct
of Survey
|
Survey
on 40 household
|
Group
IV
|
18/11/16
|
25/11/16
|
Survey
conducted
|
09
|
Seminar
presentation
|
Seminar
on “ basic concept of E-Wastage
|
Group
I
|
22/11/16
|
22/11/16
|
Seminar
Presented
|
10
|
Power
point Presentation
|
Power
point on “Harmful effects of E-wastage”
|
Group
II
|
23/11/16
|
23/11/16
|
Power
point Presented
|
11
|
Presentation
of video clippings
|
Video
Clippings on “ E-wastage management criteria”
|
Group
III
|
24/11/16
|
24/11/16
|
video
clippings Presented
|
12
|
Analysis
and presentation of survey
|
Analysis
the survey result and presentation through diagrams and tables
|
Group
IV
|
26/11/16
|
28/11/16
|
Analysis and presentation
|
Project
presentation
|
Posting
in the computer/blog
|
All
|
29/11/16
|
29/11/16
|
||
13
|
Assessment
and grading
|
Prepare
rubrics and assessment
|
Students
and teacher
|
28/11/16
|
29/11/16
|
|
14
|
Refection
and evaluation
|
Student
reflection and evaluation, Teacher refection and evaluation
|
Students
and teacher
|
29/11/16
|
29/11/16
|
|
15
|
Project
closed
|
Submitting
to the Principal
|
Teacher
|
30/11/16
|